Summer maintenance at public schools

Numerous elementary and secondary schools in Hastings and Prince Edward District School Board are getting attention over the summer. Projects range in degree of complexity and cost. The following provides a glimpse of some of the work being done. 

2009 Summer Maintenance/Renovations at HPEDSB Schools
School

 

 

 

Project

 

 

 

Approx. cost

Start date 

Bayside SS

Replace roof, Section F

$78,000 July 15
Bird’s Creek PS Create two offices from a change room $19,000 July 6
Centennial SS Renovate teacher workroom $21,000 July 13
Education Centre

Paint and re-carpet reception/lobby/hallway areas

$46,500 July 25
Education Centre Repair brickwork on front of building $25,000 June 29
Madoc Township PS Renovate computer lab $22,000 July 13
Madoc PS Convert multipurpose room in two classrooms $7,000 July 13
Moira SS Replace gym roof $76,000 July 13
Park Dale School Install metal over window panels $8,000 Late July
Prince Edward CI Install heating, ventilation, air conditioning system $2,000,000 June 29
Prince Charles School (Belleville) Replace gym roof $22,000 July 20
Queen Elizabeth School (Picton) Install parking lot/turnaround $92,000 July 8
Quinte SS Science lab renovations $1,500,000 June
S.H. Connor School Install door openers on southwest doors $6,000 Late July
Susanna Moodie Elementary Install door openers on front doors $7,000 Late July
Trenton HS Install metal over the brick by the Music Room $7,000 July 20

 Posted July 13, 2009. 